

Composite Bridge Breaks New Ground
With the successful installation of a composite arch highway bridge near Duvall, Wash. – the first of its kind on the West Coast – the Washington State Department of Transportation (WSDOT) has gained a cost-effective and sustainable alternative to traditional bridge construction.
It comes at a critical time. A federal injunction requires WSDOT to rebuild approximately 400 fish barriers under state highways in the northwest part of the state by 2030. The work will replace existing culverts beneath roadways and bridges and restore the natural stream habitats so the water flows freely and salmon, coho, chinook and steelheads can easily swim through.
Many of the fish barriers will feature buried structures. WSDOT typically uses split box culverts made from pre-cast concrete when buried structures are needed, but manufacturing the required number of pre-cast components would strain the capacity of the state’s producers. The department considered other options and chose a composite structure from AIT Bridges, a division of Advanced Infrastructure Technology. The company uses the composite arch bridge technology originally developed for the military at the University of Maine’s Advanced Structures and Composites Center. AIT Bridges has also developed GFRP deck panels that are placed across the arches.
AIT Bridges produces the hollow, tubular bridge arches (GArches) and GFRP decking (GDeck) at its factory in Brewer, Maine. Once installed on site, the arches are covered with decking and then filled with reinforcing concrete. Since 2008, the company has installed 30 GArch composite bridge systems, most on the East Coast.
The 50-foot-long bridge in Duvall is located on state Route 203 over Loutsis Creek. Since the site is steep, building a pre-cast bridge would involve renting and transporting large cranes to lift the pieces into place. For the composite components, however, general contractor Goodfellow Brothers needed only a forklift and straps. “That probably saved some money, because the pre-mobilizations to set big pieces of concrete are really expensive operations,” says Mark Gaines, WSDOT bridge and structures engineer.
Another benefit of composite bridge structures is their longevity and low lifecycle cost. “That’s a big sustainability issue. If you can have 100-plus years life and still have very minimal maintenance, that’s a win/win,” says Ken Sweeney, AIT Bridges’ group president and chief engineer. Over the long term, concrete bridges crumble and their steel reinforcements rust, eventually polluting the waters below. That doesn’t happen with composites. In addition, it takes less material to build composite bridges than concrete pre-cast structures.
Before awarding the sole source contract to AIT Bridges, WSDOT carefully reviewed all the engineering data about the composite arch bridge’s ability to withstand fire and damage caused by objects like floating logs striking it. Earthquakes were another concern. “This is the first time I’m aware of that [AIT] used the composite arch in a high-seismic zone, so we wanted to make sure that it met our seismic design requirements,” Gaines says. “We asked lots of difficult questions. But in the end, they had answers to everything we asked, and we were quite comfortable moving forward.”
The analyses showed the composite bridge could handle all the hazards. “We found that this bridge is actually more seismic-resistant than the traditional structures that are out there today,” Sweeney says. Unlike a rigid concrete structure, which can’t move easily with seismic waves, flexible composite arches can sway and then return to their original positions. The concrete reinforcement is contained within the tubes, so it moves with them. To further strengthen the bridge, AIT used carbon fiber reinforcement for the anchors that connect the arches with the concrete footers.
The company built the GArches using a braided fabric to get the required arch shape. “It also gives us the ability to put the strength of the fabric in the direction that we need it,” Sweeney explains. Workers placed the fabric over an inflated, balloon-like frame and used a vacuum infusion process with a vinyl ester resin to cure the arches. They were removed from the mold the next day.
Each of the 12 arches for the SR 203 project weigh 300 pounds and provide 54 feet of space between the two ends. To get them to the job site, AIT cut them in half and made a sleeve to splice them back together on site. The two flatbed trucks that transported them cross-country didn’t require special permits for weight or size on the three-day trip.
The 41 pultruded GDeck panels, which span a total of 49 feet, were manufactured by Creative Pultrusions using AIT’s design and delivered on a separate truck.
The general contractor removed 26,000 cubic yards of earth from the site to create room for the composite bridge installation. Once the site was ready, it took only a week-and-a-half to install the arches, screw in the decking panels and fill the arches with concrete. “Even though we knew this would be erected really quickly out in the field, the speed surprised us,” says Gaines. “It didn't take very long for them to get their tubes in place, to get all the decking in place and start the backfill process.”
After the composite arch and deck panels were erected, the contractor replaced the earth over the arch and around the sides of the structure, then built an asphalt pavement on that foundation to carry traffic over the stream. The road was closed for just over 30 days. The $8.2 million bridge reopened to traffic in August 2020.
“When you walk into a brand-new product like this, there’s a certain level of risk. But there were just no issues at all with the construction,” Gaines says. As a result, WSDOT has updated its bridge specifications to allow construction of more composite bridges. No additional projects are scheduled now, but the department is likely to build more since the cost of the composite bridge is competitive with the pre-cast structures.
Sweeney expects the success of this project, and the many benefits that composite bridges offer, will encourage their further adoption on the West Coast. “Making the sustainability case is going to be big, because one of the markets we’re trying to open up right now is California,” he adds.
Mary Lou Jay is a freelance writer based in Timonium, Md. Email comments to mljay@comcast.net.
SUBSCRIBE TO CM MAGAZINE
Composites Manufacturing Magazine is the official publication of the American Composites Manufacturers Association. Subscribe to get a free annual subscription to Composites Manufacturing Magazine and receive composites industry insights you can’t get anywhere else.